How do I display open tasks?

Shortcuts are faster: Only display active tasks in your project schedule by filtering for incomplete tasks
Philosophy
One of my pet peeves is, during weekly Webex status calls, a Program/Project Manager (PM) displays his project schedule and he continues to display all the closed or completed tasks i.e., tasks that are 100% complete. While this may not sound significant, remember that one of the tasks of a PM is information management. And information management is the art of delivering (or displaying) only the key information that stakeholders need to see. I certainly don't like having to visually wade through tasks that are no longer relevant to the project. PMs should only display open or incomplete tasks (i.e., tasks that are less than 100% complete).

Or if you need the research of why less info is more to be convinced of the benefits of keeping things simple (kinda like Apple products), check out this book "Made to Stick." This books explains beautifully why some ideas stick to people's minds and others do not. One of the six core elements of making ideas (or in our case, schedule info) sticky, is to keep it simple. Yes, KISS!

Steps

The screenshot above shows how MS Project makes it really easy to display only open (incomplete) tasks. There are two ways:
  1. Point & click: Project > Filtered for: Incomplete Tasks > Incomplete Tasks
  2. Shortcuts: [ALT] + P + F + N

How I display open tasks 
My favorite way, because it's the quickest, is to use the shortcuts. When I'm walking through the schedule with my project team, I typically have the tasks already filtered to display only open tasks. But every now and then, I've had to display all tasks (open & closed). Because I've practiced it so much, my fingers automatically hit [ALT] + P + F + A (to display all tasks). And once I'm done showing my team the closed task they had asked about, I automatically hit [ALT] + P + F + N (to filter on only open tasks).

Or when I've closed out a task by marking it at 100% complete, my fingers automatically hit the shortcut to hide the closed task. A closed task should be hidden the moment it's been marked as closed. Out of sight, out of mind, right?

Try practicing both these shortcuts for a few days to make it come automatically to your fingers.